Name of the project:
Client:
Contractor:
Adress:
Explanation:
Design project by:
Presentation of design
project fulfilling Russian norms by:
Engineering projects by:
Presentation of engineering
projects fulfilling Russian norms by:
Construction began:
Construction ended:
Duration:
Total fit-out area:
|
Shop (Women Fur) in Petrovky Passage
TIP Furs and Accessories
Fudinterkom Construction
Petrovsky Street, Moscow, Russia
All fit out works done including production of furniture and equipments
Fudinterkom Construction
Fudinterkom Construction
Fudinterkom Construction
Fudinterkom Construction
April, 2004
June, 2004
65 days
60 m2
|