Historical-Architectural Complex Odintsovo for Presidency, Waste Water Treatment Plant

Client:
Contractor:
Country/city:
Explanation:


Scope of work:

Construction began:
Construction ended:
Duration:
Numb. of workers at peek:
Built area:
Zoning:

OPK Bor
Mensel JV
Russian Fed. _ Moscow
3000 m3/day plant capacity with 3 big pools (1600 m2); Office and technical spaces' block attached to the plant (500 m2)
Reinforced concrete workmanship,
1800 m3 concrete
July 2000
October 2000
2.5 months
18 workers
2100 m2 closed constructed area
Water treatment pools, office and technical spaces' block