Central Clinical Hospital at Molodyozhny

Client:
Contractor:
Country/city:
Explanation:


Scope of work:



Construction began:
Construction ended:
Duration:
Numb. of workers at peek:
Built area:
Zoning:

Ministry of Health
Urban Insaat
Russian Fed. _ Moscow
2 basement floors;
3 typical floors (3500 m2 each);
2 technical floors
1.stage: Reinforced concrete workmanship,
9900 m3 concrete; all brick exterior walls
2.stage: All interior partition-gypsum walls (20000 m2);
false ceelings(5000 m2); partial interior finishing works
1.stage: April 1998 / 2.stage: March 2000
1.stage: August 1998 / 2.stage: August 2000
1.stage: 5 months / 2.stage: 5.5 months
1.stage: 85 workers / 2.stage: 55 workers
17500 m2 closed constructed area
Operational rooms, patient rooms, offices, ventilation spaces